M-K Engineering Co. v. Alaska Power Authority
District Court, D. Alaska
1Opinion of the Court
ORDER
HOLLAND, District Judge.
In July of 1980, the Alaska Power Authority (herein “the APA”) entered into a contract with International Engineering Company, Inc. (“IECO”), a wholly-owned subsidiary of Morrison-Knudsen Company, Inc. (“M-K”), for the design and construction management of the Tyee Lake hydroelectric project. A subsequent amendment of that contract embodied an agreement between IECO and M-K under which management of the project was transferred to M-K.
M-K filed suit in this Court in June of 1985 for breach of contract, failure to pay, promissory estoppel, and bad faith on the part…
2Cases cited10 opinions
- Scheuer v. RhodesSupreme Court of the United States · 1974
- Moor v. County of AlamedaSupreme Court of the United States · 1973
- Naartex Consulting Corporation, Russell Huff v. James G. Watt, Secretary of InteriorCourt of Appeals for the D.C. Circuit · 1983
- Jackson v. HayakawaCourt of Appeals for the Ninth Circuit · 1982
- State v. AlexAlaska Supreme Court · 1982
5 more not listed; retrieve them via the Exa API.
3Cited by1 opinion
- Alaska Cargo Transport, Inc. v. Alaska RailroadDistrict Court, D. Alaska · 1991