In January of 1948, the defendant, Pool Construction Company, was awarded a contract for a Federal public works project known as the Heyburn Dam Project. All work was performed in Creek County, Oklahoma. Pool Construction Company, as prime contractor, furnished the performance bond and payment bond as required by the Miller Act. 1

The Government brings this action in the Eastern District of Oklahoma to recover the Federal income and unemployment insurance taxes owed by the defendant, Zschach Construction, a sub-contract- or on this project, for withholding taxes it owes…

2Cases cited1 opinion

  1. United States Fidelity & Guaranty Co. v. United StatesCourt of Appeals for the Tenth Circuit · 1952

3Cited by6 opinions

  1. Koppers Company, Inc. v. Continental Casualty Company, Inc.Court of Appeals for the Eighth Circuit · 1964
  2. General Casualty Co. Of America v. United StatesCourt of Appeals for the Fifth Circuit · 1953
  3. Gypsum Contractors, Inc. v. American Surety CompanySupreme Court of New Jersey · 1962
  4. Pierce Contractors v. Peerless Casualty CompanySupreme Court of Florida · 1955
  5. United States v. Crosland Const. Co.District Court, E.D. South Carolina · 1954