West Orange Management, Inc. v. Alaimo
Appellate Division of the Supreme Court of the State of New York
1Opinion of the Court
The plaintiff commenced this action to recover a balance owed on a written agreement with the defendants to demolish and remove a building, and to recover additional costs allegedly incurred as a result of misrepresentations made by the defendants concerning the project. The defendants counterclaimed, inter alia, to recover damages for alleged breaches of the contract and for negligence in the performance of the same, including damage to a boiler during its removal and relocation to another property. After a nonjury trial, the court found, inter alia, in favor of the plaintiff on its cause of…
2Cases cited3 opinions
- Spence v. . HamNew York Court of Appeals · 1900
- Candela v. Byron Chemical Co.Appellate Division of the Supreme Court of the State of New York · 2008
- Trataros Construction, Inc. v. New York City School Construction AuthorityAppellate Division of the Supreme Court of the State of New York · 2007
3Cited by2 opinions
- Novair Mechanical Corp. v. Universal Management & Contracting Corp.Appellate Division of the Supreme Court of the State of New York · 2011
- New Ho Xin Dev., Inc. v. YangAppellate Division of the Supreme Court of the State of New York · 2020