Decided July 8, 1971No. 5025PublishedCited by 2 opinions

1Opinion of the Court

OPINION

JAMES, Justice.

In this case appellant Jack Phillips as owner entered into a “home made” written contract with appellee Ed Tacker as builder, whereby Tacker agreed to construct a certain building within a given time for Phillips for $3000.00, payable as follows: $1500.00 at the time when the cement foundation is poured, and the balance of $1500.00 within 15 days after the completion of the entire job. Trial was to a jury, which found that the building was constructed by the builder in substantial performance of the contract; and since the owner had previously paid $1500.00 on the…

2Cases cited6 opinions

  1. Van Zandt v. Fort Worth PressTexas Supreme Court · 1962
  2. Tenneco Oil Company v. Padre Drilling CompanyTexas Supreme Court · 1970
  3. Davidson v. ClearmanTexas Supreme Court · 1965
  4. George Linskie Co. v. Miller-Picking Corp.Texas Supreme Court · 1971
  5. Dill v. HelmsCourt of Appeals of Texas · 1971

1 more not listed; retrieve them via the Exa API.

3Cited by2 opinions

  1. Tacker v. PhillipsTexas Supreme Court · 1971
  2. Chiles v. BeckerCourt of Appeals of Texas · 1980

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API