Mars Associates, Inc. & Normel Construction Corp. Joint Venturers v. Health & Mental Hygiene Facilities Improvement Corp.
Appellate Division of the Supreme Court of the State of New York
1Opinion of the CourtGreenblott, J.
Plaintiff was the successful bidder for a construction contract on a facility owned by defendant. The proposal together with specifications, was put out for bidding, requesting bidders to state a base bid for the project as a whole plus the specific amount which would be added to or deducted *6from 'the (base bid for each of 16 alternarte proposals. When the contract was executed, alternates numbered 2C, 130 and 150 were expressly included in the contract. In his first cause of action, plaintiff seeks payment of $50,000, the amount of its bid under alternate 120. That provision of the proposal…
2Cited by10 opinions
- USA Network v. Jones Intercable, Inc.District Court, S.D. New York · 1990
- Allied Chemical Corp. v. Alpha Portland Industries, Inc.Appellate Division of the Supreme Court of the State of New York · 1977
- Bostwick-Westbury Corp. v. Commercial Trading Co.Civil Court of the City of New York · 1978
- In Re Adelphia Communications Corp.United States Bankruptcy Court, S.D. New York · 2007
- MARS ASSOCS., INC. & NORMEL CONSTR. CORP. v. Health & Mental Hygiene Facilities Improvement Corp.New York Court of Appeals · 1976