Post-Tensioned Systems, Inc. v. Collins & Hobbs, Inc.
Court of Appeals of Tennessee
1Opinion of the Court
OPINION
FRANKS, Judge.
Plaintiff supplied materials in the amount of $33,559.71 to a subcontractor of the prime contractor, Collins & Hobbs, who constructed an office building and parking lot complex at Memorial Hospital in Chattanooga. This suit seeking to recover from the prime contractor and hospital was dismissed by the chancellor who concluded plaintiff had failed to give its notice of lien within ten days of defendants’ filing of a notice of completion, pursuant to T.C.A., § 66-11-143.
The stipulated evidence establishes the prime contractor paid the subcontractor for the materials but the…
2Cases cited4 opinions
- Baird v. Fidelity-Phenix Fire Ins. Co.Tennessee Supreme Court · 1942
- Irvin v. BinkleyCourt of Appeals of Tennessee · 1978
- Southern Blow Pipe & Roofing Co. v. GrubbCourt of Appeals of Tennessee · 1953
- Silverman v. GossettTennessee Supreme Court · 1977
3Cited by3 opinions
- Wilson v. Mettetal (In Re Mettetal)United States Bankruptcy Court, E.D. Tennessee · 1984
- Noland Co. v. CryeCourt of Appeals of Tennessee · 1986
- Ramsay v. Westbrook Construction Co. (In re Horton Vaults, Inc.)United States Bankruptcy Court, E.D. Arkansas · 1989