Minyard v. Culotta
Louisiana Court of Appeal
1Opinion of the Court
YARRUT, Judge.
This is a suit by plaintiff, a sub-contractor, to recover damages suffered when the general contractor arbitrarily terminated his sub-contract during the progress of the work. The contract price was $1,742 for installing insulation material. At the time of termination, labor and material furnished by plaintiff to the amount of $207.14 had been paid to him.
The cost of labor and material to complete the contract was $1,194.39. The gross profit would be the difference between $1,742 and $1,194.39, or $547.61. Having been paid for labor and material already furnished up to the time…
2Cases cited7 opinions
- Dugue v. LevySupreme Court of Louisiana · 1904
- Housecraft Division of Southern Siding Co. v. JonesLouisiana Court of Appeal · 1960
- Geary v. Board of Com'rsSupreme Court of Louisiana · 1916
- Delarosa v. MisurucaSupreme Court of Louisiana · 1931
- Atchley v. HorneLouisiana Court of Appeal · 1943
2 more not listed; retrieve them via the Exa API.
3Cited by3 opinions
- Delta Paving Company v. WoolridgeLouisiana Court of Appeal · 1968
- French Jordan, Inc. v. Oilfield Sales & Serv.Louisiana Court of Appeal · 1983
- White v. Rimmer & Garrett, Inc.Louisiana Court of Appeal · 1976