Legal Opinion

Norman v. Hearne Tittle

Supreme Court of Oklahoma

Decided September 23, 1930No. 19655PublishedCited by 8 opinions

1Opinion of the Court

HALL, C.

The only question in this case presented for consideration is whether or not the lien statement was filed within the statutory time — in this case four months— after the last material was furnished or last labor was performed under the contract.

The facts in the case are substantially as follows: Lynn Norman, plaintiff in the trial court and .plaintiff in error herein, was the manager of a lumber company, and also a contractor and builder. In March, 1926, he entered into a contract with, one Rl O. McFalls and McFalls’ wife to construct for them a dwelling house in the city of Mangum,…

2Cases cited2 opinions

  1. Chicago Lumber Co. v. Merrimack River Savings BankSupreme Court of Kansas · 1893
  2. Crane Co. v. EllisOregon Supreme Court · 1911

3Cited by8 opinions

  1. Liberty Plan Co. v. Francis T. Smith Lumber Co.Supreme Court of Oklahoma · 1961
  2. Amtech Lighting Services Co. v. Payless Cashways (In Re Payless Cashways, Inc.)United States Bankruptcy Appellate Panel for the Eighth Circuit · 1999
  3. H. E. Leonhardt Lumber Co. v. Ed Wamble Distributing Co.Supreme Court of Oklahoma · 1963
  4. Cushing Country Club v. Boardman CompanySupreme Court of Oklahoma · 1963
  5. Donaldson & Yahn v. Stillwater Bldg. & Loan Ass'nSupreme Court of Oklahoma · 1935