Van Nice v. Christian Reformed Church
North Dakota Supreme Court
1Opinion of the CourtChRistiaNSON, J.
In April, 1928, the plaintiff and defendant entered into a written contract whereby the plaintiff agreed to construct a church for the defendant. The church was constructed, and, controversy having arisen between the parties in respect to several matters involved in or growing out of the transaction between them, plaintiff brought this action to recover the sum of $5,378.16, which he claims is the balance due him for the work performed and material furnished in the construction of the church. The complaint, among other things, alleges that during the course of the construction certain changes…
2Cases cited4 opinions
- Aylmer v. AdamsNorth Dakota Supreme Court · 1915
- McGregor v. Great Northern Railway Co.North Dakota Supreme Court · 1915
- State v. CrayNorth Dakota Supreme Court · 1915
- Quinlivan v. Dennstedt Land Co.North Dakota Supreme Court · 1918
3Cited by3 opinions
- Moorhead Construction Co., Inc., a Corporation, Appellee-Cross-Appellant v. City of Grand Forks, a Municipal Corporation, Appellant-Cross-AppelleeCourt of Appeals for the Eighth Circuit · 1975
- Peterson v. BoberNorth Dakota Supreme Court · 1952
- Dobler v. MalloyNorth Dakota Supreme Court · 1971