Legal Opinion

Petroline Co. v. Advanced Environmental Contractors, Inc.

Appellate Court of Illinois

Decided April 27, 1999No. 1-98-2026PublishedCited by 18 opinions

1Opinion of the CourtJustice Cousins

The plaintiff subcontractor was hired to provide equipment that was to be installed on a piece of property owned by defendants in this case. The subcontractor was not fully paid, so it filed a mechanic’s lien against the property. It provided 90 days’ notice to the owners under section 24 of the Mechanics Lien Act (770 ILCS 60/24 (West 1996)), but did not provide such notice to the mortgagee (whose interest was recorded).

The subcontractor filed suit against the owners to foreclose the lien within the statutory limitations period. The trial court dismissed the action, however, on the basis…

2Cases cited21 opinions

  1. Pliakos v. Illinois Liquor Control CommissionIllinois Supreme Court · 1957
  2. Liese v. HentzeIllinois Supreme Court · 1927
  3. People Ex Rel. Nelson v. Olympic Hotel Building Corp.Illinois Supreme Court · 1950
  4. Watson v. Auburn Iron Works, Inc.Appellate Court of Illinois · 1974
  5. Matthews Roofing Co. v. Community Bank & Trust Co.Appellate Court of Illinois · 1990

16 more not listed; retrieve them via the Exa API.

3Cited by18 opinions

  1. Parkway Bank and Trust Co. v. MeseljevicAppellate Court of Illinois · 2010
  2. Golfview Developmental Center, Inc. v. All-Tech Decorating Co. (In Re Golfview Developmental Center, Inc.)United States Bankruptcy Court, N.D. Illinois · 2004
  3. Seasons-4, Inc. v. Hertz Corp.Appellate Court of Illinois · 2003
  4. Raymond Professional Group, Inc. v. William A. Pope Co. (In Re Raymond Professional Group, Inc.)United States Bankruptcy Court, N.D. Illinois · 2009
  5. LaSalle Bank National Ass'n v. Cypress Creek 1, LPAppellate Court of Illinois · 2010

13 more not listed; retrieve them via the Exa API.