Bucko Construction Co. v. Indiana Department of Transportation
Indiana Court of Appeals
1Opinion of the Court
OPINION
FRIEDLANDER, Judge.
In November 1996, the Indiana Department of Transportation (INDOT) reviewed Bucko Construction Company, Inc.'s (Bucko) performance as a contractor with the State and, based on Bucko's deficient performance on Contract R-20974 (the Contract), reduced Buceko's prequalification rating for highway construction projects by thirty percent. Bucko administratively appealed the reduction and, after its administrative remedies proved unsuceessful, sought judicial review in December 1998. While the judicial review action was pending, Bucko filed a complaint against INDOT for…
2Cases cited8 opinions
- Indiana Department of Natural Resources v. United Refuse Co.Indiana Supreme Court · 1993
- Regester v. Indiana State Board of NursingIndiana Supreme Court · 1998
- State v. Carmel Healthcare Management, Inc.Indiana Court of Appeals · 1996
- Indiana Department of Environmental Management v. Adapto, Inc.Indiana Court of Appeals · 1999
- Indiana Education Employment Relations Board v. TuckerIndiana Court of Appeals · 1997
3 more not listed; retrieve them via the Exa API.
3Cited by2 opinions
- UTILITY CENTER, INC. v. City of Fort WayneIndiana Court of Appeals · 2012
- Utility Center, Inc., d/b/a Aqua Indiana, Inc. v. City of Fort Wayne, IndianaIndiana Court of Appeals · 2012