1Opinion of the CourtJustice Burke
*2 ¶ 1 Under recently-enacted legislation, the Illinois Power Agency (IPA) developed a long-term renewable resources procurement plan (plan) to promote renewable energy, including the implementation of three programs that provide financial support to small renewable energy generation facilities (generation facilities) that might not be economically viable otherwise. Under the plan, the generation facilities memorialize their energy production through renewable energy credits (credits) that the IPA then procures on behalf of three large electric utilities: petitioner, Commonwealth Edison Company…
2Cases cited10 opinions
- Illinois Consolidated Telephone Co. v. Illinois Commerce CommissionIllinois Supreme Court · 1983
- Solon v. Midwest Medical Records Ass'nIllinois Supreme Court · 2010
- Knolls Condominium Ass'n v. HarmsIllinois Supreme Court · 2002
- Robbins v. Board of Trustees of the Carbondale Police Pension FundIllinois Supreme Court · 1997
- Provena Covenant Medical Center v. Department of RevenueIllinois Supreme Court · 2010
5 more not listed; retrieve them via the Exa API.
3Cited by1 opinion
- Commonwealth Edison Co. v. Illinois Commerce CommissionAppellate Court of Illinois · 2019