Graettinger Tile Works v. Paine
Supreme Court of Iowa
1Opinion of the CourtEvans, J.
The defendant C. E. Paine was the principal contractor in a drainage project in Kossuth County. The plaintiff was a subcontractor, which furnished to Paine a large quantity of material for such project. As such, it filed a lien, which filing’ resulted in the tying up of funds otherwise payable to Paine. In order to obtain a release of such funds, Paine gave bond, with the defendant United States Fidelity & Guaranty Company as surety. This action was brought primarily upon the bond. However, it made the defendant Gjellefald a party defendant, under an allegation that he was the partner of…
2Cases cited2 opinions
- Thorn v. HambletonSupreme Court of Iowa · 1910
- Fuehr v. Ewert & Richter Express & Storage Co.Supreme Court of Iowa · 1917
3Cited by1 opinion
- Kirby v. HolmanSupreme Court of Iowa · 1947