Frank Salz & Sons, Inc. v. Lehr Construction Corp.

New York Supreme Court

Decided May 22, 1984PublishedCited by 2 opinions

1Opinion of the Court

OPINION OF THE COURT

Irving Lang, J.

A notice of lien requires the commencement of an action to foreclose on the lien within one year of its filing regardless of whether the nature of the lien has been changed within that period.

THE CLAIM

Petitioner herein moves for an order directing the Commissioner of the Department of Finance of the City of New York to distribute to petitioner the sum of $600 plus interest, which had previously been deposited by respondent, in discharge of a lien which petitioner held on respondent’s real property.

Respondent opposes this motion on the ground that petitioner…

2Cases cited3 opinions

  1. Phalen v. Theatrical Protective Union No. 1New York Court of Appeals · 1968
  2. In re the Thirty-fifth Street & Fifth Avenue Realty Co.Appellate Division of the Supreme Court of the State of New York · 1907
  3. In re Tumac Realty Corp.City of New York Municipal Court · 1952

3Cited by2 opinions

  1. In re Benson Park Associates LLCNew York Supreme Court · 2008
  2. Pavarini McGovern, LLC v. Waterscape Resort LLC (In re Waterscape Resort LLC)United States Bankruptcy Court, S.D. New York · 2014

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API