DeKalb County v. Rockdale Pipeline, Inc.
Court of Appeals of Georgia
1Opinion of the Court
McMurray, Presiding Judge.
Appellant DeKalb County, Georgia (“DeKalb County”) entered into a contract under which appellee Rockdale Pipeline, Inc. (“Rockdale”) was to install underground pipes for a sewer project. The contract, which was drawn by DeKalb County, specified that Rockdale would be paid $30 per cubic yard for the excavation of an estimated 7,000 cubic yards of rock; and that the rock excavation “shall be measured for payment from centerline profile, down to a depth six (6) inches below the bottom of the pipe barrel . . .” The construction drawings entitled “Plan and Profile,” which…
2Cases cited4 opinions
- Pace Construction Corp. v. Houdaille-Duval-Wright Division, Houdaille Industries, Inc.Supreme Court of Georgia · 1981
- Tidwell v. Carroll Builders, Inc.Supreme Court of Georgia · 1983
- Doyle v. Estes Heating & Air Conditioning, Inc.Court of Appeals of Georgia · 1985
- Gans v. Ga. Fed. Sav. &C. Assn.Court of Appeals of Georgia · 1986
3Cited by4 opinions
- Southland Development Corp. v. BattleCourt of Appeals of Georgia · 2005
- Georgia Magnetic Imaging, Inc. v. Greene County Hospital AuthorityCourt of Appeals of Georgia · 1995
- Harris County v. PentonCourt of Appeals of Georgia · 1993
- Harris County v. PentonCourt of Appeals of Georgia · 1993