Caribbean Engineering Co. v. United States
United States Court of Claims
1Opinion of the CourtWhitaker, Judge
The plaintiff sues to recover liquidated damages assessed against it for failure to complete on time the contract for the building of certain houses in Puerto Rico for the Puerto Rico Reconstruction Administration, and also to recover damages which it claims it suffered by reason of delays in the construction caused by the defendant.
The contract was completed 137 days after the original completion date. The plaintiff was granted an extension of time of 71 days. It was assessed liquidated damages at $200 a day for the remainder of 66 days, a total of $13,200. The principal controversy is over…
2Cases cited1 opinion
- Albina Marine Iron Works, Inc. v. United StatesUnited States Court of Claims · 1934
3Cited by1 opinion
- Cape Ann Granite Co. v. United StatesUnited States Court of Claims · 1943