General Dynamics Corp. v. United States
Supreme Court of the United States
1Opinion of the CourtJustice Scalia
We consider what remedy is proper when, to protect state secrets, a court dismisses a Government contractor’s prima facie valid affirmative defense to the Government’s allegations of contractual breach.
I
In 1988, the Navy awarded petitioners a $4.8 billion fixed-price contract to research and develop the A-12 Avenger carrier-based, stealth aircraft. The A-12 proved unexpectedly difficult to design and manufacture, and by De cember 1990, petitioners were almost two years behind schedule and spending $120 to $150 million each month to develop the A-12.
Petitioners informed the Government that the…
2Cases cited19 opinions
- Jencks v. United StatesSupreme Court of the United States · 1957
- United States v. ReynoldsSupreme Court of the United States · 1953
- Haig v. AgeeSupreme Court of the United States · 1981
- Martin v. MottSupreme Court of the United States · 1827
- Priebe & Sons, Inc. v. United StatesSupreme Court of the United States · 1947
14 more not listed; retrieve them via the Exa API.
3Cited by39 opinions
- Tecsec, Inc. v. Adobe Inc.Court of Appeals for the Federal Circuit · 2020
- Supreme Foodservice Gmbh v. United StatesUnited States Court of Federal Claims · 2013
- Faisal Nabin Kashem v. William BarrCourt of Appeals for the Ninth Circuit · 2019
- Republican Party v. New Mexico Taxation & Revenue DepartmentNew Mexico Supreme Court · 2012
- Al Haramain Islamic Foundation, Inc. v. United States Department of the TreasuryCourt of Appeals for the Ninth Circuit · 2011
34 more not listed; retrieve them via the Exa API.