Legal Opinion

Scofield v. JW Jones Construction Company

New Mexico Supreme Court

Decided July 28, 1958No. 6365PublishedCited by 29 opinions

1Opinion of the Court

McGHEE, Justice.

The plaintiff-appellee obtained a verdict for $30,000 on account of personal injuries and property damage as the result of an intersection collision between a car he was driving and a truck belonging to the defendant-appellant. Later a remittitur of $10,000 was filed after the trial court announced he would grant a new trial unless such action was taken by the appellee, leaving a net judgment in the sum of $20,000.

Numerous errors are assigned by the appellant in its efforts to secure a reversal, but we are met at the outset of our consideration by the claim of the appellee…

2Cases cited14 opinions

  1. Henderson v. DreyfusNew Mexico Supreme Court · 1919
  2. State v. FernandezNew Mexico Supreme Court · 1952
  3. Alvarado Min. & Mill Co. v. WarnockNew Mexico Supreme Court · 1919
  4. King v. McElroyNew Mexico Supreme Court · 1933
  5. Sena v. SandersNew Mexico Supreme Court · 1950

9 more not listed; retrieve them via the Exa API.

3Cited by29 opinions

  1. Dunleavy v. MillerNew Mexico Supreme Court · 1993
  2. City of Albuquerque v. AckermanNew Mexico Supreme Court · 1971
  3. State v. MinnsNew Mexico Court of Appeals · 1969
  4. Sturgeon v. ClarkNew Mexico Supreme Court · 1961
  5. State v. GonzalesNew Mexico Court of Appeals · 1990

24 more not listed; retrieve them via the Exa API.