The lawsuit involved in this appeal arose from the construction of a house by plaintiffs/appellants for appellee. Plaintiffs sued under theories of contract and quantum meruit for work done in constructing the house; appellee counterclaimed to recover damages for improperly done work. This appeal is from a judgment entered on a verdict for appellee in the amount of $25,000.

1. One item of damages sought by appellee in his counterclaim was increased interest costs on the permanent loan with which he financed the purchase of the house. He contended that the increased…

2Cases cited8 opinions

  1. Worthey v. HolmesSupreme Court of Georgia · 1982
  2. Williams v. KennedySupreme Court of Georgia · 1977
  3. Ambassador College v. GoetzkeSupreme Court of Georgia · 1979
  4. Denton v. EtheridgeCourt of Appeals of Georgia · 1945
  5. Rose Mill Homes, Inc. v. MichelCourt of Appeals of Georgia · 1980

3 more not listed; retrieve them via the Exa API.

3Cited by4 opinions

  1. Department of Transportation v. Dalton Paving & Construction, Inc.Court of Appeals of Georgia · 1997
  2. Esprit Log & Timber Frame Homes, Inc. v. WilcoxCourt of Appeals of Georgia · 2010
  3. Denny v. NuttCourt of Appeals of Georgia · 1988
  4. Stinchcomb v. WrightCourt of Appeals of Georgia · 2006

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API