Keating v. Federal Energy Regulatory Commission
Court of Appeals for the D.C. Circuit
1Opinion of the Court
Opinion for the Court filed by Chief Judge SENTELLE.
SENTELLE, Chief Judge:
The Federal Energy Regulatory Commission granted Joseph Keating a license to build a hydroelectric power plant in 1992. At Keating’s request, the Commission stayed the four-year statutory deadline for commencing construction on the project to allow Keating to obtain the necessary water rights. Over fifteen years after the license issued, the Commission lifted the stay and Keating’s license expired. Keating now petitions for review of the Commission’s decision to lift the stay, arguing that the record does not support…
2Cases cited7 opinions
- Baltimore Gas & Electric Co. v. Natural Resources Defense Council, Inc.Supreme Court of the United States · 1983
- Office of Personnel Management v. RichmondSupreme Court of the United States · 1990
- Federal Power Commission v. Metropolitan Edison Co.Supreme Court of the United States · 1938
- Papago Tribal Utility Authority v. Federal Energy Regulatory Commission, Arizona Public Service Company and Arizona Power Authority, IntervenorsCourt of Appeals for the D.C. Circuit · 1980
- Burlington Northern & Santa Fe Railway Co. v. Surface Transportation BoardCourt of Appeals for the D.C. Circuit · 2005
2 more not listed; retrieve them via the Exa API.
3Cited by39 opinions
- Pierce v. Securities & Exchange CommissionCourt of Appeals for the D.C. Circuit · 2015
- Safari Club International v. SalazarCourt of Appeals for the D.C. Circuit · 2013
- WA Alliance of Tech. Workers v. DHSCourt of Appeals for the D.C. Circuit · 2022
- In Re Polar Bear Endangered Species Act ListingDistrict Court, District of Columbia · 2011
- District Hospital Partners, L.P. v. SebeliusDistrict Court, District of Columbia · 2013
34 more not listed; retrieve them via the Exa API.