Bellefleur v. United States Finishing Co.
Supreme Court of Connecticut
1Opinion of the CourtHaines, J.
The question at issue involves the rights of the parties under a contract. The finding, which is not contested, discloses that this contract was in the form of a written order, executed by the defendant and duly accepted by the plaintiff, and was in form as follows:
“The United States Finishing Company
Engineering Department Providence, It. I.
Date Dec. 21, 1927.
A. C. Bellefleur & Son Co.
% 136 Garfield Ave.,
New London, Conn.
Please send us:
1—36" Bullard Vertical Boring Mill.
This machine to be taken for a 30 day trial. Can be returned if not satisfactory. All as per their Mr. Bellefleur’s letter.
Pr…
2Cases cited2 opinions
- Springfield Engine Stop Co. v. SharpMassachusetts Supreme Judicial Court · 1903
- Isaacs v. MacdonaldMassachusetts Supreme Judicial Court · 1913
3Cited by1 opinion
- Sommer Metalcraft Corp. v. Indianapolis MacHinery Co.Indiana Court of Appeals · 1962