Parkinson v. Amundson
Utah Supreme Court
1Opinion of the Court
HENRIOD, Justice.
Appeal from a finding that in the purchase of a house plaintiffs overpaid defendants by mistake. Affirmed. Costs to respondents.
Defendants agreed to build a house for plaintiffs.. A contract was signed in April 1950. The consideration was $14,500. Plaintiffs made some payments. When nearly completed the house was appraised by a Veterans’ Administration appraiser, who set the completed fair value at $13,750. Thereupon the parties wrote another contract for that figure.
Prior to completion some changes were made with respect to details of construction. A dispute arose as to who…
2Cases cited1 opinion
- Beagley v. United States Gypsum Co.Utah Supreme Court · 1951
3Cited by1 opinion
- Turtle Management, Inc. v. Haggis Management, Inc.Utah Supreme Court · 1982