In re Thornton Co.
District Court, M.D. Pennsylvania
1Opinion of the Court
JOHNSON, District Judge.
On September 6, 1923, the Standard Iron Works of Scranton, Pa., contracted with the Thornton Company, of Scranton, Pa., to furnish and deliver structural steel and corrugated iron sheeting for a coal breaker building, f. o. b. cars Millview, Pa., together with necessary bolts, and to erect a new breaker building at Eorksville, Pa., for the price of $11,550, payable when all of the material was delivered and erected in the breaker building. While the structural material was on the ground of the Thornton Company, but before any of it was erected into the breaker…
2Cases cited1 opinion
- Thompson v. LarsenOregon Supreme Court · 1926
3Cited by2 opinions
- In the Matter of Universal Medical Services, Inc., Debtor. Appeal of Irving H. Kutcher, Trustee in BankruptcyCourt of Appeals for the Third Circuit · 1972
- In Matter of Universal Medical Services, Inc.District Court, E.D. Pennsylvania · 1971