Legal Opinion

Caddell Construction Co. v. United States

United States Court of Federal Claims

Decided September 7, 2007No. 04-461CPublishedCited by 1 opinion

1Opinion of the Court

*408 OPINION & ORDER

FUTEY, Judge.

This government contract case is before the court following a trial on liability and damages. Plaintiff claims, on behalf of its steel fabrication subcontractor, that defendant provided structural steel drawings that allegedly contained conflicts, errors, omissions, and/or inadequate details. Plaintiff maintains that the purportedly defective drawings resulted in a delay and additional costs. Plaintiff, therefore, requests an equitable adjustment of $2,782,149.52. Defendant argues that the designs were not defective and that plaintiff, not defendant, was the cause…

2Cases cited20 opinions

  1. United States v. SpearinSupreme Court of the United States · 1918
  2. San Carlos Irrigation and Drainage District v. The United StatesCourt of Appeals for the Federal Circuit · 1989
  3. Emily Malone D/B/A Precision Cabinet Company v. The United StatesCourt of Appeals for the Federal Circuit · 1988
  4. Wunderlich Contracting Co. v. United StatesUnited States Court of Claims · 1965
  5. Servidone Construction Corporation, Plaintiff/cross-Appellant v. The United StatesCourt of Appeals for the Federal Circuit · 1991

15 more not listed; retrieve them via the Exa API.

3Cited by1 opinion

  1. Penzel Constr. Co. v. Jackson R-2 Sch. Dist., Warner-Nease-Bost Architects & Henthorn, Sandmeyer & Co.Missouri Court of Appeals · 2017

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API