Gamm Construction Co. v. Townsend
Appellate Court of Illinois
1Opinion of the Court
Mr. PRESIDING JUSTICE SEIDENFELD
delivered the opinion of the court:
Gamm Construction Co., as a subcontractor under an agreement with the contractor, Donald Richards, sued to establish a mechanics lien based upon the performance of concrete and masonry work on the property of Alicia Townsend performed prior to the termination of the contract by the defendant contractor. The court entered judgment for the plaintiff in the amount of $10,500. Defendants appeal, claiming that the judgment is against the manifest weight of the evidence and that the amount of the lien was incorrectly established.
In…
2Cases cited15 opinions
- Geist v. LehmannAppellate Court of Illinois · 1974
- Herbert Shaffer Assoc., Inc. v. First Bank of Oak ParkAppellate Court of Illinois · 1975
- Hill Behan Lumber Co. v. MarcheseAppellate Court of Illinois · 1971
- Hunter v. DeMayAppellate Court of Illinois · 1970
- Moulding-Brownell Corp. v. E. C. Delfosse Construction Co.Appellate Court of Illinois · 1940
10 more not listed; retrieve them via the Exa API.
3Cited by7 opinions
- Wilmette Partners v. HamelAppellate Court of Illinois · 1992
- Oakleaf v. Oakleaf & Associates, Inc.Appellate Court of Illinois · 1988
- Barrows v. MacO, Inc.Appellate Court of Illinois · 1981
- Pathman Construction Co. v. Hi-Way Electric Co.Appellate Court of Illinois · 1978
- Bell v. Yale Development Co.Appellate Court of Illinois · 1981
2 more not listed; retrieve them via the Exa API.