Legal Opinion

General Electric Supply Corp. v. Wiley Electric Co.

Ohio Court of Appeals

Decided November 9, 1933No. 579PublishedCited by 1 opinion

1Opinion of the Court

OPINION

By HAMILTON, PJ.

It will be noted that the petition fails to allege that a statement of the amount' due was furnished to the Insurance Company within the ninety days after acceptance of the work, as provided for in §2365-3, GC.

The trial court sustained the demurrer, presumably on authority of Atkinson et v Orr-Ault Construction Co, 124 Oh St, 100. Plaintiff, not desiring to plead further, judgment was entered on the sustaining of the demurrer and the petition was dismissed. Error is prosecuted from that judgment.

Plaintiff in error contends that the petition states a cause of action at…

2Cases cited4 opinions

  1. Ewing v. JonesIndiana Supreme Court · 1892
  2. Million v. Metropolitan Casualty InsuranceIndiana Court of Appeals · 1930
  3. Concrete Steel Co. v. Metropolitan Casualty InsuranceIndiana Court of Appeals · 1930
  4. Eagle Indemnity Co. v. McGeeIndiana Court of Appeals · 1931

3Cited by1 opinion

  1. Thomas Steel, Inc. v. Wilson Bennett, Inc.Ohio Court of Appeals · 1998

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API