Olson Construction Co. v. United States ex rel. Cooper Supply Co.
Court of Appeals for the Tenth Circuit
1Opinion of the Court
SETH, Circuit Judge.
This is an action brought under the-Miller Act, 40 U.S.C.A. § 270a, by a supplier for recovery of a balance due for materials delivered to a subcontractor.. The suit is brought against the subcontractor, the prime contractor, Olson Construction Company, and its surety, United States Fidelity & Guaranty Company.. The subcontractor, Chickasha Plumbing & Heating Company, was not itself bonded for the job in question which was the construction of a hospital at Schilling Air Force Base, Kansas. It was engaged as a subcontractor on several other projects at the same time,…
2Cases cited7 opinions
- Columbia Digger Co. v. RectorDistrict Court, W.D. Washington · 1914
- Wait v. Homestead Building Ass'nWest Virginia Supreme Court · 1918
- Borough of Totowa v. American Surety Co. of New YorkSupreme Court of New Jersey · 1963
- American Casualty Company of Reading, Pennsylvania, a Corporation v. Line Materials Industries, a Division of McGraw Company, a CorporationCourt of Appeals for the Tenth Circuit · 1964
- Wyandotte Coal & Mining Co. v. Wyandotte Paving & Construction Co.Supreme Court of Kansas · 1916
2 more not listed; retrieve them via the Exa API.
3Cited by2 opinions
- Industrial Investment Corp. v. RoccaIdaho Supreme Court · 1979
- Olson Construction Company v. United StatesCourt of Appeals for the Tenth Circuit · 1964