Sterling Eng. & Mfg. Corp. v. Jennings
Superior Court of Pennsylvania
1Opinion of the Court
Opinion by
Whitmore, J.,
The plaintiff brought suit in assumpsit against the defendants, appellants, to recover the balance due on a contract in writing between the parties dated June 5, 1929, accepted by the plaintiff on June 7, 1929, for the sale and delivery f. o. b. cars at Boston, Mass., of certain machinery consisting of boiler feeder, receiver and air valve.
The defendants filed an affidavit of defense admitting the execution of the written contract but alleging, inter alia, that the machinery and equipment, when installed, did not give the results warranted and guaranteed by the…
2Cases cited2 opinions
- Gianni v. Russell Co., Inc.Supreme Court of Pennsylvania · 1924
- Bloom to Use of General Motors Acceptance Corp. v. LundbergSuperior Court of Pennsylvania · 1929
3Cited by8 opinions
- Bardwell v. the Willis CompanySupreme Court of Pennsylvania · 1953
- Madison-Kipp Corp. v. Price Battery Corp.Supreme Court of Pennsylvania · 1933
- Hoesch v. FreedmanSuperior Court of Pennsylvania · 1933
- East Coast Fi. Corp. v. LinckSuperior Court of Pennsylvania · 1931
- Berger v. Pittsburgh Auto Equipment Co.Supreme Court of Pennsylvania · 1956
3 more not listed; retrieve them via the Exa API.