Rainbow Electric Co. v. Bloom
Appellate Division of the Supreme Court of the State of New York
1Opinion of the Court
In an action to foreclose a mechanic’s lien and to recover damages for breach of contract, (1) the defendants third-party plaintiffs Bloom and Slavin appeal (a) from a judgment of the Supreme Court, Queens County (Kaplan, J.H.O.), dated November 18, 1985, which is in favor of the plaintiff Rainbow Electric Co., Inc. (hereinafter Rainbow) in the principal sum of $12,286, and (b) from a judgment of the same court, also dated November 18, 1985, which is in favor of the defendant third-party defendant Bamboo of China Constructors, Ltd. (hereinafter Bamboo), in the principal sum of $18,583.35,…
2Cases cited2 opinions
- Arc Electrical Construction Co. v. George A. Fuller Co.New York Court of Appeals · 1969
- Hartman v. TravisAppellate Division of the Supreme Court of the State of New York · 1981
3Cited by9 opinions
- Spectrum Painting Contractors, Inc. v. Kreisler Borg Florman General Construction Co.Appellate Division of the Supreme Court of the State of New York · 2009
- Kuhn v. KoberAppellate Division of the Supreme Court of the State of New York · 1994
- Regal Lumber Co. v. Buck, New York County Courts1993
- Rure Associates, Inc. v. DiNardi Construction Corp.Court of Appeals for the Second Circuit · 1990
- Worlock Paving Corp. v. CamperlinoAppellate Division of the Supreme Court of the State of New York · 1995