Chatterjee Fund Management, L.P. v. Dimensional Media Associates
Appellate Division of the Supreme Court of the State of New York
1Opinion of the Court
—Order, Supreme Court, New York County (Herman Cahn, J.), entered February 11, 1998, which granted defendants’ motion for summary judgment dismissing plaintiffs complaint, unanimously affirmed, with costs.
When parties do not intend to be bound until their agreement is reduced to writing and signed, there is no contract in the interim (Brown Bros. Elec. Contrs. v Beam Constr. Corp., 41 NY2d 397, 399; Scheck v Francis, 26 NY2d 466, 469-470), even if the parties have orally agreed upon all the terms of the proposed contract (R.G. Group v Horn & Hardart Co., 751 F2d 69, 74). In this case, the…
2Cases cited5 opinions
- BROWN BROS. v. Beam Constr.New York Court of Appeals · 1977
- Scheck v. FrancisNew York Court of Appeals · 1970
- Songbird Jet Ltd., Inc. v. Amax Inc.District Court, S.D. New York · 1984
- Frutico, S.A. de C.V. v. Bankers Trust Co.District Court, S.D. New York · 1993
- Dunhill Securities Corp. v. Microthermal Applications, Inc.District Court, S.D. New York · 1969
3Cited by18 opinions
- Giunta v. DingmanCourt of Appeals for the Second Circuit · 2018
- Jordan Panel Systems Corp. v. Turner Construction Co.Appellate Division of the Supreme Court of the State of New York · 2007
- Prospect Street Ventures I, LLC v. Eclipsys Solutions Corp.Appellate Division of the Supreme Court of the State of New York · 2005
- J.E. Capital, Inc. v. Karp Family AssociatesAppellate Division of the Supreme Court of the State of New York · 2001
- Dale v. GentryAppellate Division of the Supreme Court of the State of New York · 2009
13 more not listed; retrieve them via the Exa API.