Devore v. Barstow Company

Supreme Court of South Carolina

Decided June 2, 1932No. 13421PublishedCited by 1 opinion

1Opinion of the Court

The opinion of the Court was delivered by

Mr. Justice StabeEr.

The facts out of which this action arose, briefly stated, are these: In August, 1927, W. S. Barstow & Co., Inc., hereinafter referred to as Barstow, contracted, for a specified consideration, with Lexington Water Power Company, hereinafter referred to as the power company, to build a large dam across Saluda River, and to cut all trees and clear all growth within the area to be flooded. Thereafter, on February 4, 1928, J. E- Triplette Lumber Company, hereinafter referred to'as Tripplette, contracted with Barstow to cut and remove all…

2Cited by1 opinion

  1. Bob Hammond Construction Co. v. Banks Construction Co.Court of Appeals of South Carolina · 1994