Devore v. Barstow Company
Supreme Court of South Carolina
1Opinion of the Court
The opinion of the Court was delivered by
Mr. Justice StabeEr.
The facts out of which this action arose, briefly stated, are these: In August, 1927, W. S. Barstow & Co., Inc., hereinafter referred to as Barstow, contracted, for a specified consideration, with Lexington Water Power Company, hereinafter referred to as the power company, to build a large dam across Saluda River, and to cut all trees and clear all growth within the area to be flooded. Thereafter, on February 4, 1928, J. E- Triplette Lumber Company, hereinafter referred to'as Tripplette, contracted with Barstow to cut and remove all…
2Cited by1 opinion
- Bob Hammond Construction Co. v. Banks Construction Co.Court of Appeals of South Carolina · 1994