Cohen v. Lewis
Court of Appeals of Texas
1Opinion of the CourtHiggins, J.
Cohen built for Lewis a corrugated iron shed under an agreement that Lewis would pay therefor the cost of construction plus 10 per eent. Upon*bills submitted by Cohen, Lewis paid Cohen $2,733.70 for building the shed. Later Lewis brought this suit against Cohen and the H. M. Cohen Lumber & Building Company to recover $1,303.70. It was alleged that the reasonable cost of the shed, plus 10 per cent., was $1,430, and the sum of $2,733.70 was paid by mutual mistake and miscalculation of the parties. In the alternative it was alleged that the payment was made upon the false and fraudulent…
2Cases cited7 opinions
- Golden v. OdiorneTexas Supreme Court · 1923
- Burton-Lingo Co. v. BeyerCourt of Appeals of Texas · 1904
- H., E. & W. T. R'y Co. v. SnellingTexas Supreme Court · 1883
- Warnock v. MillsTexas Commission of Appeals · 1927
- Texas Hardware & Implement Mut. Fire Ins. v. Dallas Trust & Savings BankCourt of Appeals of Texas · 1927
2 more not listed; retrieve them via the Exa API.
3Cited by2 opinions
- Commercial Casualty Ins. Co. v. HiltonCourt of Appeals of Texas · 1932
- Minnehoma Financial Co. v. JohnsonCourt of Appeals of Texas · 1952