Pace Construction Corp. v. Houdaille-Duval-Wright Division, Houdaille Industries, Inc.
Court of Appeals of Georgia
1Opinion of the Court
Banke, Judge.
This is a suit by the appellee subcontractor to recover for labor and materials furnished in connection with a construction project. The appellants are the general contractor and the two sureties on the latter’s performance bond. They contend that the subcontract contained a mandatory arbitration clause and accordingly moved below for an order “staying discovery and all other judicial proceedings in the instant action until such time as all subcontract claims existing between [the parties] have been submitted to and resolved by arbitration in accordance with relevant contractual…
2Cases cited6 opinions
- Shanferoke Coal & Supply Corp. v. Westchester Service Corp.Supreme Court of the United States · 1935
- Binswanger Glass Co. v. Beers Construction Co.Court of Appeals of Georgia · 1977
- Paine, Webber, Jackson & Curtis, Inc. v. McNealCourt of Appeals of Georgia · 1977
- West Point-Pepperell, Inc. v. Multi-Line Industries, Inc.Supreme Court of Georgia · 1973
- Burden v. ThomasCourt of Appeals of Georgia · 1961
1 more not listed; retrieve them via the Exa API.
3Cited by7 opinions
- Phillips Construction Co. v. Cowart Iron Works, Inc.Supreme Court of Georgia · 1983
- Pace Construction Corp. v. Houdaille-Duval-Wright Division, Houdaille Industries, Inc.Supreme Court of Georgia · 1981
- Tasco Industries, Inc. v. Fibers & Fabrics of GeorgiaCourt of Appeals of Georgia · 1982
- Phillips Construction Co. v. Cowart Iron Works, Inc.Court of Appeals of Georgia · 1982
- Pace Construction Corp. v. Houdaille-Duval-Wright DivisionCourt of Appeals of Georgia · 1981