Pace Construction Corp. v. Houdaille-Duval-Wright Division, Houdaille Industries, Inc.

Court of Appeals of Georgia

Decided October 1, 1980No. 60365PublishedCited by 7 opinions

1Opinion of the Court

Banke, Judge.

This is a suit by the appellee subcontractor to recover for labor and materials furnished in connection with a construction project. The appellants are the general contractor and the two sureties on the latter’s performance bond. They contend that the subcontract contained a mandatory arbitration clause and accordingly moved below for an order “staying discovery and all other judicial proceedings in the instant action until such time as all subcontract claims existing between [the parties] have been submitted to and resolved by arbitration in accordance with relevant contractual…

2Cases cited6 opinions

  1. Shanferoke Coal & Supply Corp. v. Westchester Service Corp.Supreme Court of the United States · 1935
  2. Binswanger Glass Co. v. Beers Construction Co.Court of Appeals of Georgia · 1977
  3. Paine, Webber, Jackson & Curtis, Inc. v. McNealCourt of Appeals of Georgia · 1977
  4. West Point-Pepperell, Inc. v. Multi-Line Industries, Inc.Supreme Court of Georgia · 1973
  5. Burden v. ThomasCourt of Appeals of Georgia · 1961

1 more not listed; retrieve them via the Exa API.

3Cited by7 opinions

  1. Phillips Construction Co. v. Cowart Iron Works, Inc.Supreme Court of Georgia · 1983
  2. Pace Construction Corp. v. Houdaille-Duval-Wright Division, Houdaille Industries, Inc.Supreme Court of Georgia · 1981
  3. Tasco Industries, Inc. v. Fibers & Fabrics of GeorgiaCourt of Appeals of Georgia · 1982
  4. Phillips Construction Co. v. Cowart Iron Works, Inc.Court of Appeals of Georgia · 1982
  5. Pace Construction Corp. v. Houdaille-Duval-Wright DivisionCourt of Appeals of Georgia · 1981

2 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API