Legal Opinion

Dickinson & Gillespie, Inc. v. Kirkwood

Supreme Court of Minnesota

Decided February 3, 1939No. 31,890PublishedCited by 1 opinion

1Opinion of the Court

Loring, Justice.

Plaintiff sought to recover from the defendants a claimed balance of $331.86 on the agreed contract price for constructing a house in St. Louis Park. The defendants counterclaimed for inferior materials and defective workmanship in the sum of $750 and as a second counterclaim sought to recover special damages for two months’ delay in the completion of the house for occupancy. They set up that they were required to find another apartment and to pay rent therefor for a period of two months and were put to additional expense in moving and storing their furniture and household…

2Cases cited4 opinions

  1. Frohreich v. GammonSupreme Court of Minnesota · 1881
  2. Liljengren Furniture & Lumber Co. v. MeadSupreme Court of Minnesota · 1890
  3. Smith v. AltierSupreme Court of Minnesota · 1931
  4. Glaubitz v. MeyerSupreme Court of Minnesota · 1921

3Cited by1 opinion

  1. Sward v. NashSupreme Court of Minnesota · 1950