This is an action by the plaintiff, a fabricator of precast construction materials, upon a written contract to recover the balance due under said contract.

The plaintiff manufactured and erected for the defendant general contractor certain concrete double tee slabs used in the construction of a commercial apartment complex. The total contract price was $31,000 and the defendant made a payment of $15,000, leaving a remaining balance due of $16,000.

The defendant acknowleged the contract but in its answer and counterclaim alleged that the double tee slabs were defective and…

2Cases cited7 opinions

  1. Jones v. ElliottNebraska Supreme Court · 1961
  2. Muller Enterprises, Inc. v. GerberNebraska Supreme Court · 1965
  3. Socony Mobil Oil Company v. KlapalDistrict Court, D. Nebraska · 1962
  4. Midland-Ross Corporation v. SwartzNebraska Supreme Court · 1970
  5. Graham v. AndersonNebraska Supreme Court · 1931

2 more not listed; retrieve them via the Exa API.

3Cited by8 opinions

  1. Roskop Dairy v. GEA Farm Tech.Nebraska Supreme Court · 2015
  2. Wiebe Construction Co. v. School District of MillardNebraska Supreme Court · 1977
  3. Griffith v. GriffithNebraska Supreme Court · 1988
  4. Central National Insurance Company Of Omaha v. Devonshire Coverage CorporationCourt of Appeals for the Eighth Circuit · 1977
  5. Hein v. M & N Feed Yards, Inc.Nebraska Supreme Court · 1980

3 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API