Porter v. Fairland & Shelbyville Turnpike Co.
Indiana Supreme Court
From the Shelby Circuit Court.
1Opinion of the CourtNiblack, J.
This was a proceeding in the court below, by the appellants, to enjoin the collection of certain benefits claimed to have been *599assessed against their lands, on account of the location and proposed construction of a line of road by the Fairland and Shelbyville Turnpike Company. There was a temporary restraining order. The appellees answered in two paragraphs, and a demurrer to the second paragraph was overruled, to which the appellants excepted. The appellants then replied to the said second paragraph.of the answer. A demurrer was sustained to the reply, to which an exception was also…
2Cases cited1 opinion
- Webb v. Brandywine Junction Turnpike Co.Indiana Supreme Court · 1876