1Opinion of the Court

JACOBSON, Judge.

In this appeal, the Court is requested to review an action for breach of contract caused by fraudulent misrepresentation.

The plaintiff-appellee, Sanner Construction Company (Sanner) brought an action against defendant-appellant, Hunter Construction Company (Hunter) for breach of contract and subsequent damages resulting from a fraudulent misrepresentation. The case was submitted to a jury on the theory of fraud. The jury returned a verdict in favor of Sanner in the sum of $178,597.39 as compensatory damages and One Dollar as punitive damages. Hunter has appealed from this…

2Cases cited13 opinions

  1. Lutfy v. R. D. Roper & Sons Motor Co.Arizona Supreme Court · 1941
  2. Campbell v. ChatwinArizona Supreme Court · 1967
  3. Waddell v. WhiteArizona Supreme Court · 1940
  4. Weatherford v. AdamsArizona Supreme Court · 1926
  5. Milam v. MilamArizona Supreme Court · 1966

8 more not listed; retrieve them via the Exa API.

3Cited by14 opinions

  1. United California Bank v. Prudential Insurance Co. of AmericaCourt of Appeals of Arizona · 1983
  2. Dawson v. WithycombeCourt of Appeals of Arizona · 2007
  3. Harry Bechtel and Cathleen Bechtel, Husband and Wife v. Liberty National Bank, a National Banking AssociationCourt of Appeals for the Ninth Circuit · 1976
  4. Echols v. Beauty Built Homes, Inc.Arizona Supreme Court · 1982
  5. Kaufman v. LanghoferCourt of Appeals of Arizona · 2009

9 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API