Morion by defendant for a new trial on the minutes.

1Opinion of the CourtMcAdam, J.

The contract here, like the one in Phelan v. Mayor, 119 N. Y. 86, provides that the time during which the work of completion may be delayed by acts of the city shall be determined by the commissioner of public works. Such provision proved fatal to the plaintiff in that case, but is not controlling here, for the contract sued on contains other prolusions more germane to this controversy, to-wit: (1.) “ In case said building shall not be completed within five hundred working days as aforesaid, the architect in charge of said building shall certify, in writing, what portion of said excess of…

2Cases cited7 opinions

  1. Heryford v. DavisSupreme Court of the United States · 1880
  2. Clark v. . DevoeNew York Court of Appeals · 1891
  3. Del Genovese v. Third Avenue RailroadAppellate Division of the Supreme Court of the State of New York · 1897
  4. Byron v. . LowNew York Court of Appeals · 1888
  5. Phelan v. Mayor of New YorkNew York Court of Appeals · 1890

2 more not listed; retrieve them via the Exa API.

3Cited by1 opinion

  1. Peck v. Reid, New York County Courts1910