Cesere v. Town of Windham
Supreme Court of New Hampshire
1Per curiam
The question we decide in this appeal is whether an amendment to the Town of Windham’s zoning ordinance, which was adopted several months after intervenor Equity Property Associates II had begun negotiating with the Windham Planning Board regarding site approval for a condominium project that is prohibited by the amended ordinance, bars the planning board from granting site development approval for the project. We hold that it does.
The intervenor in September 1979 first sought site development approval for a clustered condominium project in Windham to be known as Fox Hill. After several…
2Cases cited6 opinions
- Piper v. MeredithSupreme Court of New Hampshire · 1970
- Patenaude v. Town of MeredithSupreme Court of New Hampshire · 1978
- Henry and Murphy, Inc. v. Town of AllenstownSupreme Court of New Hampshire · 1980
- Town of Freedom v. GillespieSupreme Court of New Hampshire · 1980
- Buxton v. Town of ExeterSupreme Court of New Hampshire · 1977
1 more not listed; retrieve them via the Exa API.
3Cited by2 opinions
- Hanselv. City of KeeneSupreme Court of New Hampshire · 1993
- Morin v. City of SomersworthSupreme Court of New Hampshire · 1988