Serafini Construction Co. v. State
New York Court of Claims
1Opinion of the CourtRichard S. Heller, J.
This claim arises out of a contract for the reconstruction of 1.54 miles of State highway running through the Village of Waterloo. The contract was dated June 1, 1956, and had a completion date of June 1, 1957. Claimant commenced work under the contract in June, 1956.
By September, 1956, claimant was prepared to commence pouring concrete pavement and had sufficient men and equipment on the job to complete the paving by November, 1956. On September 10, 1956, claimant was notified that it would not be permitted to commence paving until a decision had been reached in regard to the relocation or…