B & M Siding Corp. v. Sucu
Massachusetts District Court, Appellate Division
1Opinion of the CourtCowdrey, P.J.
This'is an action in contract to recover a balance allegedly due for work performed by the plaintiff corporation on the defendant’s residence. The trial court .entered judgment for the plantiff in the amount of $1,537.50.
On August 8, 1977, the parties executed a written contract for the installation of vinyl siding and styrofoam insulation, and for certain roofing and downspout work on the defendant’s home for a total cost of $6,375.00. The agreement was expressly rendered conditional upon the defendant’s securing of a $5,000.00 construction loan. Additional miscellaneous clauses of the…
2Cases cited18 opinions
- Loranger Construction Corp. v. E. F. Hauserman Co.Massachusetts Supreme Judicial Court · 1978
- Andre v. MaguireMassachusetts Supreme Judicial Court · 1940
- Glazer v. SchwartzMassachusetts Supreme Judicial Court · 1931
- Zarthar v. SalibaMassachusetts Supreme Judicial Court · 1933
- DiMare v. CapaldiMassachusetts Supreme Judicial Court · 1957
13 more not listed; retrieve them via the Exa API.