Tufano Contracting Corp. v. Port of New York Authority
Appellate Division of the Supreme Court of the State of New York
1Opinion of the Court
In an action to recover (1) payment of a balance allegedly due under a construction contract; (2) for extra work done there*833under; and (3) damages for its breach, the defendant appeals: (a) from an order of the Supreme Court, Queens County, entered April 30, 1962, which granted plaintiff’s motion for partial summary judgment of $65,774.65, with interest, on the first cause of action for the balance due under the contract; which severed the remaining 14 causes of action; and which directed that the judgment to be entered on such first cause of action shall provide that acceptance of payment of…
2Cases cited1 opinion
- Fleder v. ItkinNew York Court of Appeals · 1945
3Cited by1 opinion
- KEC Corp. v. New York State Environmental Facilities Corp.New York Supreme Court · 1973