Walter v. Brothers
Ohio Court of Appeals
1Opinion of the CourtLemert, J.
An examination of the record before us discloses that the contract entered into between the parties herein was substantially performed between the 2nd day of December, 1929 and latter part of December, 1929 or the first part of January, 1930, and that afterwards, to-wit: on or about March 26th, 1930, before the purchasers of the property moved into the house, plaintiff claims that he changed the steam return and adjusted the radiator valves. Taking the dates from March 26th, 1930 to July 12th, 1930, being about three and a half months, the only work or labor performed or material furnished…
2Cases cited1 opinion