1Opinion of the CourtH. R. Carroll, J.

This case arises out of a contract signed by Michigan State University on July 20, 1969, with Ackerman Construction Company for the renovation of one of its dormitories. Ackerman, in turn, subcontracted a portion of the work to the plaintiff in the amount of $40,504.80. On December 2, 1969, the University made its final payment to Ackerman in the sum of $50,200. Ackerman then deposited the check in its account at the Bank of Lansing and simultaneously made a check out to Reichenbach for $20,504.80, the amount due and owing under the subcontract. However, the bank refused to honor the check…

2Cases cited22 opinions

  1. Tuttle v. Department of State HighwaysMichigan Supreme Court · 1976
  2. Williams v. PolgarMichigan Supreme Court · 1974
  3. Connelly v. Paul Ruddy's Equipment Repair & Service Co.Michigan Supreme Court · 1972
  4. Regents of the University v. Employment Relations CommissionMichigan Supreme Court · 1973
  5. Pittman v. City of TaylorMichigan Supreme Court · 1976

17 more not listed; retrieve them via the Exa API.

3Cited by16 opinions

  1. Precopio v. City of DetroitMichigan Supreme Court · 1982
  2. WT ANDREW COMPANY v. Mid-State Surety Corp.Michigan Supreme Court · 1996
  3. Lefever v. American Red CrossMichigan Court of Appeals · 1981
  4. Dagen v. Village of BaldwinMichigan Court of Appeals · 1987
  5. People v. LeFloreMichigan Court of Appeals · 1983

11 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API