Legal Opinion

Perini Corp. v. United States

United States Court of Claims

Decided July 20, 1967No. 228-58Published

1Opinion of the Court

OPINION

COWEN, Chief Judge.

The central issue in this contract case is whether a substantial variation from an estimated quantity in contract specifications constitutes a changed condition within the meaning of the standard Changed Conditions article, when the facts establish that the variation was foreseen by the contractor and should reasonably have been anticipated by the Government. That question, and a host of related ones, have generated protracted proceedings before the contracting officer, the Corps of Engineers Claims and Appeals Board, and in this court.1 What is unique here is that…

2Cases cited33 opinions

  1. United States v. Carlo Bianchi & Co.Supreme Court of the United States · 1963
  2. Brawley v. United StatesSupreme Court of the United States · 1878
  3. United Contractors, a Co-Partnership Consisting of James E. Ward, Elkin Morris and Andrew J. Dickies v. The United StatesUnited States Court of Claims · 1966
  4. Kaiser Industries Corporation v. The United StatesUnited States Court of Claims · 1965
  5. John A. Johnson Contracting Corp. v. United StatesUnited States Court of Claims · 1955

28 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API