1Opinion of the Court

Frank Holt, Justice.

The appellee, a subcontractor, brought this action against the appellant, a general contractor, for the balance due on a construction contract. The contract provided that appellee would furnish labor and materials and construct a roof for a school complex according to the architect’s revised plans and specifications. Appellant paid appellee $36,000 of the $43,486 contract price but refused to pay the $7,486 balance until appellee corrected alleged defects in the roof to conform to the architect’s requirements. Appellee orally amended his complaint by increasing his claim…

2Cases cited4 opinions

  1. Brower Manufacturing Co. v. WillisSupreme Court of Arkansas · 1972
  2. Fanning v. Hembree Oil CompanySupreme Court of Arkansas · 1968
  3. Ray v. FletcherSupreme Court of Arkansas · 1968
  4. Fields v. SugarSupreme Court of Arkansas · 1972

3Cited by5 opinions

  1. Fields v. Volkswagen of America, Inc.Supreme Court of Oklahoma · 1976
  2. Firestone Tire & Rubber Co. v. LittleSupreme Court of Arkansas · 1982
  3. Faver v. FaverSupreme Court of Arkansas · 1979
  4. Faver v. FaverSupreme Court of Arkansas · 1979
  5. Firestone Tire & Rubber Co. v. LittleSupreme Court of Arkansas · 1982

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API