Tennessee Gas Pipeline Company, a Division of Tenneco, Inc. v. Federal Power Commission, Columbia Gas Transmission Corporation, Intervenors
Court of Appeals for the D.C. Circuit
1Per curiam
Tennessee Gas Pipeline Company (Tennessee) petitions this court to review and set aside a letter order of the Federal Power Commission (the Commission) issued July 31, 1972, which rejected a “Purchased Gas Cost Tracking Rate Increase” filed by Tennessee. We find that the July 31st order was in direct conflict with a prior Commission order, and direct the July 31st order to be set aside. 1
A “tracking rate change” enables a pipeline to adjust its rates to reflect certain cost increases without following the detailed procedures required for a general rate change. In 1970 the Commission…
2Cases cited1 opinion
- City of Chicago v. Federal Power CommissionCourt of Appeals for the D.C. Circuit · 1967
3Cited by6 opinions
- Mitchell Energy Corporation v. Federal Power Commission, (Two Cases)Court of Appeals for the Fifth Circuit · 1975
- Mobil Oil Corporation v. Federal Power CommissionCourt of Appeals for the D.C. Circuit · 1978
- Union Electric Co. v. Federal Energy Regulatory CommissionCourt of Appeals for the D.C. Circuit · 1989
- Transcontinental Gas Pipe Line Corp. v. Federal Energy Regulatory CommissionCourt of Appeals for the D.C. Circuit · 1981
- Transcontinental Gas Pipe Line Corporation v. Federal Energy Regulatory Commission, Public Service Commission of the State of New York, Intervenor. Transcontinental Gas Pipe Line Corporation v. Federal Energy Regulatory CommissionCourt of Appeals for the D.C. Circuit · 1981
1 more not listed; retrieve them via the Exa API.