Legal Opinion

L.A. Wenger Contracting Co. v. Kreisler Borg Florman General Construction Co.

Appellate Division of the Supreme Court of the State of New York

Decided August 9, 2007PublishedCited by 1 opinion

1Opinion of the Court

Order, Supreme Court, New York County (Judith J. Gische, J.), entered November 1, 2006, which denied defendant’s motion for summary judgment, unanimously reversed, on the law, with costs, the motion granted, and the complaint dismissed. The Clerk is directed to enter judgment accordingly.

Defendant was the contractor and construction manager pursuant to a 1999 contract with the City Department of Design and Construction (DDC) for the construction of a building to be used by the City Administration for Children’s Services. Plaintiff was the general construction subcontractor.

Defendant’s…

2Cases cited3 opinions

  1. Nationwide General Insurance v. Investors Insurance Co. of AmericaNew York Court of Appeals · 1975
  2. Lewis v. Safety Disposal System of Pennsylvania, Inc.Appellate Division of the Supreme Court of the State of New York · 2004
  3. In re the Arbitration between Pharmacia & Upjohn Co. & Elan Pharmaceuticals, Inc.Appellate Division of the Supreme Court of the State of New York · 2004

3Cited by1 opinion

  1. FCI Group, Inc. v. City of New YorkAppellate Division of the Supreme Court of the State of New York · 2008