E. E. Stump Well Drilling, Inc. v. Willis
Supreme Court of Virginia
1Opinion of the CourtCarrico, C.J.
This is an appeal in a mechanic’s lien case. At the heart of the controversy is Code § 43-16,1 which provides that if “the owner” is compelled to complete a building because of the general contractor’s default, the amount expended by “the owner” for such completion shall have priority over all mechanics’ liens placed on the building. The sole question for decision is whether the appellee, Patricia Ann Willis, was “the owner” of the subject property within the meaning of Code § 43-16 so that the amount she expended to complete the building was entitled to priority over a *447mechanic’s lien filed…
2Cases cited2 opinions
- Wallace v. BrumbackSupreme Court of Virginia · 1941
- Loyola Federal Savings & Loan Ass'n v. Herndon Lumber & Millwork, Inc.Supreme Court of Virginia · 1978
3Cited by6 opinions
- Gunther v. CantrellFairfax County Circuit Court · 1988
- Atkins v. Jim Carpenter Co.Stafford County Circuit Court · 1990
- Boehl v. BMW Restoration Co. of Va., Inc.Loudoun County Circuit Court · 1993
- Springfield Engineering Corp. v. Three Score Development Corp.Stafford County Circuit Court · 1992
- R. C. Lee Carpet & Tile, Inc. v. Core Construction Corp.Spotsylvania County Circuit Court · 1988
1 more not listed; retrieve them via the Exa API.