Legal Opinion

Passarelli v. J-Mar Development, Inc.

Nevada Supreme Court

Decided June 26, 1986No. 16394PublishedCited by 12 opinions

1Opinion of the Court

OPINION

2Per curiam

J-Mar Development, Inc. (J-Mar) claimed balances due on a construction contract. The matter was called to trial on November 28, 1984, and neither Authur Passarelli (Passarelli) nor his counsel appeared. After reviewing the documents and hearing the testimony of witnesses, the lower court entered judgment against Passarelli for the sum of $13,247.60 along with interest and costs.

On December 24, 1984, a motion was filed requesting the court to set aside the judgment and grant a new trial. This motion was pursuant to NRCP 59(a)(3), or alternatively, NRCP 60(b)(1). 1 We agree with…

3Cases cited2 opinions

  1. Hotel Last Frontier Corp. v. Frontier Properties, Inc.Nevada Supreme Court · 1963
  2. Brinkley v. StateNevada Supreme Court · 1985

4Cited by12 opinions

  1. NC-DSH, INC. v. GarnerNevada Supreme Court · 2009
  2. Stoecklein v. Johnson Electric, Inc.Nevada Supreme Court · 1993
  3. WILLARD VS. BERRY-HINCKLEY INDUS.Nevada Supreme Court · 2020
  4. Dagher v. DagherNevada Supreme Court · 1987
  5. Bauwens v. EvansNevada Supreme Court · 1993

7 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API